Transit City

Promotional billboard indicating the original seven proposed LRT lines.

Transit City was a plan for developing public transport in Toronto, Ontario, Canada. It was first proposed and announced by then-Toronto Mayor David Miller and Chair of the Toronto Transit Commission (TTC) Adam Giambrone on 16 March 2007. The plan called for the construction of seven new light rail lines along the streets of seven priority transit corridors, which would have eventually been integrated with existing rapid transit, streetcar, and bus routes.[1] Other transit improvements outlined in the plan included upgrading and extending the Scarborough RT line, implementing new bus rapid transit lines, and improving frequency and timing of 21 key bus routes.[2][3][4] The plan integrated public transportation objectives outlined in the City of Toronto Official Plan, the TTC Ridership Growth Strategy and Miller's 2006 election platform.

Since the official announcement of the plan, preliminary engineering work and environmental impact assessments were done for the construction of the light rail lines.[5] Public meetings have been held to generate community discussion. The plan was initially reported to be funded by both municipal and provincial levels of government. However, as the Government of Ontario later decided to postpone a portion of its capital funding to Transit City, which met with much public and political controversy, construction plans were changed causing longer delays in construction start dates. Construction of one of the lines began in December 2009.

On 1 December 2010, Rob Ford, who was elected mayor in the 2010 municipal election, took office saying that the first job of the new transit commission to be appointed on 8 December would be to "stop spending money on a project we don't need anymore". Ford campaigned on a platform proposing expansion of the subway system, instead of implementing light rail lines. Ford acknowledged that he will need council's support to put an end to Transit City.[6] In early 2012, Toronto City Council voted in favour of motions to resume work on the Sheppard, Eglinton and Finch LRT lines, as well as replacing the Scarborough RT, defeating Rob Ford's campaign for subways.[7][8] The master agreement for these lines was signed on 28 November 2012. While these projects were originally proposed under Transit City, they are now part of Metrolinx's implementation of The Big Move regional transportation plan.[9]

Projects

Map of proposed light rail and bus rapid transit lines
A map of the proposed light rail transit (LRT) and bus rapid transit (BRT) lines according to Transit City. The existing subway/RT lines include the still future northern extension of the Yonge-University-Spadina line and the proposed eastern extension of the Scarborough RT. Future stations to be built, both subway and LRT, are written in italics. Proposed LRT stops on each LRT line are not shown. Note that the Scarborough RT is shown as an existing subway/RT line, although its revitalization plan is part of Transit City.

The plan proposed 120 km (74.6 mi) of tram or electric light rail along seven routes. The proposed network would carry 175 million riders a year, of which 75 million would be new TTC users.[10] The seven proposed corridors have been divided into two project priority phases: current and planned. In May 2009, the Metrolinx CEO, Robert Prichard, announced that after further study, the proposed project was being scaled down, with shortened routes or deferrals to fit within the dedicated provincial funding for Transit City, not factoring in the province's March 2010 announcement that it was deferring $4 billion in funding.[11]

The Toronto Transit Commission (TTC) was prepared to fund the entire cost of the network over a longer period of time. The highest priority was assigned to the Sheppard East, Eglinton Crosstown LRT and Etobicoke-Finch West LRT lines, and to the revitalization of the Scarborough RT line, which was projected to be built by 2020. In addition to the mentioned lines, it was likely that some sort of link would be established between the two lines, so that they could share a single storage facility. The TTC completed the environmental impact assessments for most of these lines, the first one being completed for the Sheppard East line.[12] The construction of this line commenced on December 2009[13] but was stopped a year later by newly elected mayor Rob Ford.[14]

Light rail transit

The following routes were to be constructed and opened by 2020. Development on the Scarborough RT line was also considered to be priority (see below).

The following projects are undergoing environmental assessments and construction was to begin after 2020 and be completed by 2030 at the latest:

Scarborough RT

Part of the Transit City project is the revitalization of the existing Scarborough RT rapid transit line. This project will extend the existing line eastwards from its present terminus at McCowan Station to three additional stops. The first proposed station will be at Bellamy Road to serve the Consilium Place business area and the second on Progress Avenue, east of Markham Road, serving Centennial College Progress Campus. The line will then curve north to Sheppard Avenue East, connecting with the Sheppard East LRT. A new environmental class assessment is being made to further continue the line north into the neighbourhood of Malvern over a former railbed just east of Markham Road. In the future, an in-fill station may be added at Brimley Road.

The existing service is approaching the end of the operational life of its ICTS fleet; as trains are no longer built to that line's specification, a replacement is needed. While an upgraded form of ICTS (Mark II Vehicles designed by Bombardier) had been considered, the current recommendation is to implement the LRT/tram technology used for Transit City to save on the fleet and track maintenance costs currently incurred by this unique-within-Toronto system. All renovations and extension constructions are to be completed by 2020. However, under Rob Ford, the renovated and extended Scarborough RT will become a part of the Eglinton Crosstown LRT instead and renamed Eglinton–Scarborough Crosstown line.

Bus rapid transit

The TTC was also planning to begin six new bus rapid transit (BRT) right-of-way lines once the tramline or light rail transit construction was complete, some of which are temporary until a subway extension occurs while one of them is already in service. The proposed routes are:

The York University Busway may stop service once the Spadina subway extension to Vaughan Metropolitan Centre station is complete. Likewise, creating a BRT line on Yonge Street depends on the fate of the proposed Yonge subway extension; if the subway extension is not approved, then work on the BRT line may commence.

Funding and costs

In April 2009, Finch West, Eglinton Crosstown, and the Scarborough RT upgrade and extension secured $7.2 billion in funding from the province,[21] while the Sheppard East LRT has received $613 million in funding from the province, and $317 million in federal funding.[22] In November 2007, the TTC provided an updated estimate of the costs of the proposal in its capital budget.[23] The project cost to be paid by the Government of Ontario is $8.3 billion.

On 15 June 2007, the Government of Ontario announced its MoveOntario 2020 plan, that calls for a major overhaul and expansion of the Greater Toronto Area's transit systems, including the Transit City proposal, that will cost an estimated $17.5 billion in provincial and federal funding over a 12-year period.[24] The provincial government proposes to provide two-thirds of the funds ($11.5 billion), and will ask the federal government to pay the remaining one-third ($6 billion).[24] However, Prime Minister Stephen Harper's government is currently not committed to this spending plan.[24] The province's $17.5 billion MoveOntario 2020 plan calls for a total number of 52 transit projects in the GTA to be funded, with 95% of the projects completed by the year 2020.[25]

Controversy

On 18 June 2009, Miller requested federal funding from the Harper government's $12-billion stimulus spending to purchase new streetcars as part of the Transit City plan. The city faced a deadline of 27 June 2009 to commit to the $1.2-billion deal signed with Bombardier for the 204 streetcars. Miller and Premier Dalton McGuinty flew to Thunder Bay to announce their funding for the new streetcars, hoping to convince the Harper government to come up with its one-third share of the cost. Federal Transport Minister John Baird rejected the request outright. Baird stated that streetcar funding clearly failed to meet the stimilus bill's requirement that the funds would have to be spent in 2 years, as that was meant to put money into the economy quickly to buoy demand and staving off deflation, while Transit City would have been a long-term project. Also the stimulus required funds to be spent on infrastructure in the municipality where the application is granted in order to create local employment, whereas the jobs created by building streetcars would be in Thunder Bay and not Toronto. Baird noted that Toronto was the only one out of 2,700 applicants that didn't meet the eligibility criteria.[26][27][28]

On 25 March 2010, the Ontario provincial government announced their decision to postpone $4 billion of funding to Metrolinx for the MoveOntario 2020 project, which included funding for Transit City. Toronto Mayor David Miller had expressed discontent and condemned Ontario Premier Dalton McGuinty, who had earlier promised to provide full funding for Transit City in order for it to be built before the 2015 Pan American Games in Toronto.

The initial investment was to create approximately 100,000 jobs.[29][30] The stated reason for the decision is a $21.3 billion deficit in the 2010 provincial operating budget.[31] Standard economic metrics, however, show that as stimulus, Transit City adds significantly to provincial tax revenues, and given the province's 50-year amortization, the plan overall reduces Ontario's annual budget deficit.[32] This caused widespread debate, protests and criticism of premier Dalton McGuinty by politicians and local groups. As a result of the postponement, the plan has since been scaled down and expected completion dates have been further pushed back.[33]

The delay in funding, according to Miller, meant that the priority LRT lines (Scarborough RT, Etobicoke-Finch West and Eglinton Crosstown) would not be able to meet their planned construction and opening dates; work on the Sheppard East line would proceed, however, as its construction had already begun.[34] Despite the controversy over the funding, Metrolinx had still negotiated a deal with Bombardier Transportation for a new fleet of trams or light rail vehicles which would be used on future Transit City lines.[35]

Since the announcement, the City of Toronto and community groups have begun a lobbying campaign to restore funding, similar to the campaign leading to the initial funding. Mayor Miller has condemned the funding delay and requested riders to contact their Members of Provincial Parliament to have the government restore the funding. Other Transit City advocates also petitioned and organized rallies to promote the immediate construction of the projects.[36]

The Public Transit Coalition was launched by common transit riders to counter the delay in Transit City funding. On 21 April 2010, the group held an event at the Toronto City Hall Council Chambers.[37]

Economic effect

Transit City was expected to create approximately 200,000 new jobs in Ontario from $8.3 billion invested.[38] This includes operation, construction, and economic stimulus effect of spending. Unemployment reached 9% in 2010, the GTA's highest level since 1995.[39]

The Ontario government's promised funding for Transit City creates short-term economic growth of $12.4 billion per year,[40] adding in the near-term 2.1% to Ontario's GDP, according to the American Public Transportation Association.[41]

According to the Federation of Canadian Municipalities research, Transit City was to produce a first-year GDP gain of $17.3 billion, were all the money to be spent in the first year. After five years the project levels off to add $8.0 billion per year to GDP, with each $1 billion spent on transit adding 0.06% to Canada's GDP annually. This compares closely to US Congressional testimony, which shows infrastructure investment to stimulate annual GDP at a multiplier of 1.69 within one year, or $14 billion per year for Transit City.[42] Both studies count direct impact of spending only.[43]

In addition to this direct consequence, long-term indirect effects on business costs, productivity, and consumer spending from reduced congestion and travel costs create an additional $14.1 billion of value annually to Ontario's economy.[38] Other indirect effects not measured are improved air quality and public health and reduced carbon emissions from extending rapid transit to 1.1 million more people.

Ontario taxes capture 12% of Ontario's GDP, meaning that Transit City's stimulus effect directly adds to Provincial tax revenue.[44][45] Transit City's direct economic impact of $12.4 billion per year nets the Ontario treasury $1.4 billion in annual tax revenue. Indirect effects on congestion and transportation costs produce an additional $1.7 billion per year in tax revenue. Government of Canada Bonds currently offer 4% interest for a 10-year term.[45] Transit City's $8.3 billion expansion funding, if amortized over 10 years at prevailing bond rates, cost the Province $1.2 billion per year.[46] With Provincial tax revenues of $3.1 billion per year, Transit City easily makes up its financing cost.

See also

References

  1. Kalinowski, Tess (24 April 2009). "TTC picks Bombardier to supply streetcars". Toronto Star. Retrieved 25 April 2009.
  2. Kalinowski, Tess (21 August 2009). "TTC unveils proposal to improve bus service". Toronto Star. Retrieved 21 August 2009.
  3. "Transit City Bus Plan" (PDF). Toronto Transit Commission. 21 August 2009. Retrieved 21 August 2009.
  4. http://www3.ttc.ca/PDF/About_the_TTC/Transit_City_Bus_Plan.pdf
  5. "Transit City Light Rail Plan: Status Update for February 2009" (PDF). Toronto Transit Commission. 2 February 2009. Retrieved 15 February 2008.
  6. CBC.ca 1 December 2010
  7. Church, Elizabeth (8 February 2012). "TTC chair defeats Rob Ford, wins bid to bring transit above-ground". Toronto: The Globe and Mail. Retrieved 8 February 2012.
  8. Church, Elizabeth; Kelly Grant (23 March 2012). "Transit defeat leaves Ford on rocky ground". Toronto: The Globe and Mail. Retrieved 23 March 2012.
  9. Tess Kalinowski (28 November 2012). "TTC, Metrolinx finally sign off on LRTs". Toronto Star. Retrieved 28 November 2012.
  10. Kalinowski, Tess; John Spears (17 March 2007). "Success driven by TTC: Miller". GTA. Toronto Star. pp. B.1. Retrieved 17 June 2007.
  11. Kalinowski, Tess (5 May 2010). "Toronto's Trancity slower, shorter". News. Toronto Star. Retrieved 5 May 2010.
  12. Sheppard Avenue East Light Rail Transit (LRT) – Background
  13. http://transit.toronto.on.ca/archives/weblog/2009/12/23-transit_ci.shtml
  14. http://news.nationalpost.com/2010/12/01/the-war-on-the-car-is-over-and-so-is-transit-city-rob-ford/
  15. 1 2 3 4 5 6 "Transit City Report". Toronto Transit Commission Report. City of Toronto. 21 March 2007. Retrieved 17 June 2007.
  16. "Delay to Sheppard East LRT raises hopes of possible subway line". Scarborough Mirror. 2012-08-24. Retrieved 25 October 2012.
  17. Steve Munro (2006-11-23). "Waterfront West LRT plans". Archived from the original on 2015-03-03. Retrieved 2015-03-02.
  18. Inside Toronto: LRT planned for 2015 to run along Lake Shore Boulevard West has now been shelved by city officials
  19. University of Toronto Scarborough: Re-Imagine: Benefit students now and in the future
  20. https://www.thestar.com/news/gta/transportation/2016/01/20/revised-scarborough-subway-plan-eliminates-2-stations.html
  21. "Province Moving Transit Projects Forward" (Press release). Ontario Ministry of Transportation. 1 April 2009. Retrieved 28 October 2009.
  22. "Ontario Moves Forward With Sheppard Transit Line" (Press release). Premier of Ontario. 15 May 2009. Retrieved 28 October 2009.
  23. 2008-2012 Capital Program and 10-Year Capital Forecast
  24. 1 2 3 Gray, Jeff (16 June 2007). "Ontario planning $11.5-billion in public transit". Toronto: The Globe and Mail. Retrieved 18 June 2007.
  25. Kalinoswski, Tess (16 June 2007). "A $17,5B transit promise". Toronto Star. Retrieved 17 June 2007.
  26. John Baird's profane truth - The Globe and Mail
  27. High stakes in streetcar game - Toronto Star
  28. Baird says no to stimulus money for T.O. streetcars - CTV Toronto News
  29. Economic Impact of Public Transportation Investment (PDF), American Public Transportation Association, October 2009 (pg. 28, Exhibit 3-3, Jobs Generated in the US per Billion Dollars of Spending on Public Transportation)
  30. Todd Litman (23 February 2010), Evaluating Public Transit Benefits and Costs: Best Practices Guidebook (PDF), Victoria Transport Policy Institute (pg. 59, Economic Development Impacts)
  31. http://www.fin.gov.on.ca/en/budget/ontariobudgets/2010/bk_managing.html Ontario Ministry of Finance: 2010 Ontario Budget: Backgrounder Managing Responsibly
  32. http://www.nowtoronto.com/news/story.cfm?content=174785 Now Magazine - It’s a money train: Transit City's a fast track to boom, not a ticket to budget doom
  33. Kalinowski, Tess; Rider, David (29 April 2010). "Province's pledge: 4 Transit City lines in 10 years". Toronto Star. Retrieved 2010-04-29. “Initial work by Metrolinx suggests that the four Transit City projects can reasonably be completed in 10 years, while achieving the required savings of $4 billion in the first five years,” says the April 27 letter to City Manager Joe Pennachetti obtained by the Toronto Star.
  34. "Budget slashes billions from Toronto transit expansion". CBC News. 26 March 2010. Archived from the original on 30 March 2010.
  35. Kalinowski, Tess (12 April 2010). "Metrolinx negotiations signal green light for Transit City". The Star. Toronto.
  36. http://network.nationalpost.com/NP/blogs/toronto/archive/2010/04/17/fight-begins-to-save-transit-city.aspx
  37. http://www.cp24.com/servlet/an/local/CTVNews/20100421/100421_transitcity/20100421/?hub=CP24Home
  38. 1 2 Economic Impact of Public Transportation Investment (PDF), American Public Transportation Association, October 2009 (pg. iii, Table within Summary)
  39. Unemployment hits 15-year high in Ontario, Toronto Star, 6 June 2009
  40. Economic Impact of Public Transportation Investment (PDF), American Public Transportation Association, October 2009 (pg. ii, Table within Summary, Summary of the Short-term Economic Impact per Billion Dollars of National Investment in Public Transportation)
  41. http://www.fin.gov.on.ca/en/budget/ontariobudgets/2010/ch2c.html Ontario Budget 2010
  42. Mark Zandi, Chief Economist, Moody's Economy.com (21 January 2009), Congressional Testimony for the 2009 US Stimulus Bill (PDF) pg. 9, Table 2. Fiscal Stimulus Bang for the Buck
  43. Macroeconomic Impacts of Spending and Level-of-Government Financing (PDF), Federation of Canadian Municipalities, 31 May 2008 (pg. 6, Table 1. GDP Impacts of Additional Infrastructure Spending)
  44. http://www.fin.gov.on.ca/en/budget/ontariobudgets/2010/ch2d.html Ontario Budget 2010 shows 09-10 tax revenue of $65.9 billion
  45. 1 2 http://www.fin.gov.on.ca/en/budget/ontariobudgets/2010/ch2b.html Ontario 2010 Budget shows Ontario Gross Domestic Product
  46. Amortization calculator
This article is issued from Wikipedia - version of the 9/9/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.