Siti Hydroelectric Power Station

Siti Hydroelectric Power Station
Location of Siti Hydroelectric Power Station in Uganda
Country Uganda
Location Siti, Bukwo District
Coordinates 01°15′00″N 34°38′13″E / 1.25000°N 34.63694°E / 1.25000; 34.63694Coordinates: 01°15′00″N 34°38′13″E / 1.25000°N 34.63694°E / 1.25000; 34.63694
Status Proposed
Commission date 2017 (Expected)
Power generation
Units planned 1 x 5 MW
1 x 16.5 MW
Nameplate capacity 21.5 MW

Siti Hydroelectric Power Station, commonly referred to as Siti Power Station, is a proposed 21.5 megawatts (28,800 hp) mini hydropower station in Uganda.[1]

Location

The power station will be located across River Siti, in Siti Parish, Bukwo District, in northeastern Uganda, near the International border with the Republic of Kenya. This location, lies on the northeastern slopes of Mount Elgon, within Mount Elgon National Park, at an altitude of about 2,000 metres (6,600 ft), above sea level.

Overview

The power station is a run of river, mini hydropower installation, with planned capacity of 21.5 Megawatts. The impact assessment studies have been conducted and presented. One private developer, Elgon Hydro Siti Private, has applied for the development rights to the project.[2] When completed, the power station will be the largest power generating installation in northeastern Uganda. The power generated from this power plant will supply the local communities in Bukwo District and the balance will be integrated into the national power grid.

Construction timeline

In October 2014, the Electricity Regulatory Authority (ERA), licensed nine new renewable energy projects, including Siti Hydroelectric Power Station. The power complex will consist of two run of river generation units; Siti I with capacity of 5 Megawatts and Siti II, with capacity of 16.5 Megawatts. Construction is expected to begin in December 2014 and last approximately 24 months.[3]

See also

References

  1. Deep Earth (31 October 2013). "Power Watchdog Assessing 21.5MW Siti Proposed Plant". DeepEarthInt.com. Retrieved 12 July 2014.
  2. "Elgon Hydro Siti (Private) Public Hearing For A 21.5MW Generation License Concluded". Electricity Regulatory Authority - Uganda (ERA). 28 October 2013. Retrieved 12 July 2014.
  3. Sanya, Samuel (22 October 2014). "ERA Licenses 9 Renewable Energy Projects". New Vision (Kampala). Retrieved 23 October 2014.
This article is issued from Wikipedia - version of the 3/28/2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.