SM-1 was a 2-megawatt nuclear reactor developed by the United States Atomic Energy Commission for the US Army Nuclear Power Program (ANPP) in the mid-1950s. The compact "package" reactor was designed to produce electricity and generate heat for remote military facilities. The first, the SM-1, served as the Army's primary training facility to train reactor operations personnel from all three services (Army, Navy and Air Force). In 1954, the Department of Defense placed the US Army in charge of all military nuclear power plants except those used for propulsion by the US Navy. The Army's Chief of Engineers established the US Army Engineer Reactors Group in April 1954, and decided to construct the SM-1 facility at the Corps of Engineers headquarters at Fort Belvoir, Virginia, about 18 miles south of Washington, D.C.. About 800 personnel were trained on the SM-1 during its operational life, from 1957 to 1973. The power plant was shut down in March 1973, and is monitored within a "restricted access" section of the post. Inspectors enter the shut-down operations control room every decade or so, and the building may be demolished "about 50 years" after the reactor core was removed, possibly around 2030.[1]
Construction of the SM-1 facility
Research and development of the reactor design was conducted in 1952-54 at the Oak Ridge National Laboratory, under the guidance of the Package Power Group. Funding for the reactor was approved in 1954 and bids to construct the facility were received from 18 companies, ranging in price from $2 million to $7 million.[2] According to Time magazine of 18 July 1955, the Army selected the low bid ($2,096,753), submitted by the American Locomotive Company (ALCO Products) of Schenectady, New York, and awarded the contract in December 1954.[3]
The name "SM-1" stands for Stationary, Medium-size reactor, prototype #1. The pressurized-water reactor (PWR) design developed by the AEC was a heterogeneous, water-cooled and water-moderated, stainless steel system, using highly enriched (93%) uranium dioxide mixture as fuel.[4]
The term "package" in the name Army Package Power Reactor refers to the program objective of designing a compact nuclear power plant whose components could be packed for delivery to remote facilities aboard large military transport aircraft. The SM-1 served as the prototype for the SM-1A power plant, which was constructed at Fort Greely, Alaska between 1960-62. The reactor core itself was compact, about the size of a household dishwasher.[5]
At a press conference held on 19 August 1954, (then) Major General Sturgis, Chief of Engineers, announced the plan by the Army and the AEC to build the "package" power plant at Fort Belvoir. A location in a "closed area" of the garrison had been selected, near a point at which Accotink Bay (aka, Gunston Cove) joins the Potomac River. The general said the design of the package reactor resembles the nuclear power plant on the US Navy's (newly launched) nuclear submarine Nautilus. He also said the reactor could be housed in a building 29 feet wide, 42 feet high and 80 feet long. The Army was sending out a request for proposals, that day, to "33 qualified bidders", and companies were being asked to come up with a "competitive lump-sum bid", rather than a cost-plus estimate.[6] On 14 December 1954, the AEC announced that the contract was being given to American Locomotive Company of New York, whose $2 million bid was the lowest of the 18 proposals received.[7] Asking companies to submit a lump-sum bid was hailed, at that time, as a sign of how much progress had been made in reactor power plant design by mid-1954, such that companies now had sufficient experience and could calculate costs with confidence.
Construction of the building to house the reactor began on 5 October 1955 in the southeast "corner" of Fort Belvoir, Virginia, alongside Gunston Cove, off the Potomac River. According to a news note in the December 1955 Bulletin of the Atomic Scientists, "Construction of the 'package' or portable reactor has been started at Fort Belvoir, VA. Alco Products is the contractor for the Defense Department and the AEC. The reactor will generate about 2,000 kilowatts of electricity, enough for a community of about 5,000 people."[8] Alco Products supplied the reactor, pressurizer and steam generator, while Westinghouse Electric Corporation supplied the canned-rotor pumps, General Electric supplied the turbine and generator, the Lummus Company supplied the condenser, and Minneapolis-Honeywell installed the controls. By late October 1955, the Army pushed ALCO to accelerate construction towards a completion date of 10 July 1957.[9] As a result, all major work was completed by March 1957.
Reactor goes critical, April 1957
Construction was completed in 18-months, the SM-1 reactor achieved first criticality on 8 April 1957, and the plant was formally opened in a public ceremony on 29 April 1957. Designed as a small-scale, pressurized-water, commercial nuclear power plant the power output from the SM-1 was connected to the local electrical grid. Thus, the SM-1 and Fort Belvoir hold the distinction of delivering the first electricity for public use in America, coming online several months before the (much larger, $55 million) Shippingport Reactor (in December 1957.)[10]
According to a June 1957 report in the industry magazine POWER, "Normal operation (of the SM-1) will need a total of 29 men. Operators will be high-school graduates with 1-year training, led by engineers."[11] The location of the Army's nuclear reactor training facility alongside Gunston Cove explains why the floating MH-1A came to be tested at Fort Belvoir in April 1966.
Facility hailed as a model for "Atoms for Peace"
The successful operation of the SM-1 was promoted by the Department of Defense as a demonstration of President Eisenhower's "Atoms for Peace" program. Shortly after it was placed in operation in 1957, the Pentagon invited a group of foreign defense military attaches stationed in Washington D.C. to tour the Fort Belvoir facility. A 30-second news video of that 1957 visit shows military officers from Cuba, Costa Rica and Portugal, amongst the group invited inside the reactor control room.
Reactor closed in 1973, building reopens as museum
Plans to decommission the SM-1 reactor were announced in June 1972, and the reactor was shut down for the last time on 16 March 1973: four members of the first group of operators trained in 1957 participated in the shutdown ceremony.[12] According to a 1998 US Army report on the Army Reactor Program, during its 16 years of operations the facility trained some 800 nuclear operations specialists.[13] During its operational life, the SM-1 reactor had its core replaced twice. According to a January 2001 report compiled by the Department of Energy, the total amount of uranium-235 supplied for the SM-1's three cores was 72.7 kilograms: the U-235 was enriched to 93 percent. The spent fuel from the first core was sent to the Idaho National Engineering and Environmental Laboratory (the INEEL, originally known as the Idaho National Reactor Testing Station) and the fuel from the SM-1's second and third cores was sent to the Savannah River Site.[14]
In April 1975, the reactor building was reopened to the public as a museum until the mid 1980s when it was again closed to the public.[12]
SM-1 photo gallery
-
SM-1 before the "HP mod"
-
ANPP brochure
-
Sketch of the reactor shield, pressure vessel, core and instruments
-
Operation limits
-
Startup procedure
-
Control room: control rod position indicators in the foreground
-
Electrical panel, control room
-
Nuclear instrument panel, control room
-
Turbine (generator in background)
-
Steam-jet air ejectors, turbine deck
External sources
- Special Features of Military Package Power Reactors Report issued 8 August 1956 by Oak Ridge National Laboratory Applied Nuclear Physics Division
References
- ↑ THE JOURNAL, online Northern Virginia news, Tuesday 22 March 2011, “A Snippet of History: Fort Belvoir’s Nuclear Power Plant”; report by David Kerr; accessed 11 March 2012.
- ↑ ORNL: The First 50 Years; accessed 12 March 2012.
- ↑ TIME, 18 July 1955 "Atomic Energy: Power Package"; accessed 10 March 2012.
- ↑ The Bulletin of the Atomic Scientists, June 1957 (Vol.13, issue 6: page 229); "News Roundup: Package Power Reactor in Operation" prepared by Helen C. Allison; accessed 11 March 2012.
- ↑ ORNL-2128 Reactors- Special Features of Military Package Power Reactors, report of Oak Ridge National Laboratory, Applied Nuclear Physics Division, issued 8 August 1956; accessed 12 March 2012.
- ↑ New York Times, 20 August 1954, page 17; "Army Will Build Atom Power Unit"; accessed 14 March 2012.
- ↑ New York Times, 15 December 1954, page 24; "Atom Job Given Locomotive Firm"; accessed 14 March 2014.
- ↑ The Bulletin of the Atomic Scientists, December 1955 (Vol.11, issue 10: page 378); "News Roundup: Package Reactor" prepared by Helen C. Allison; accessed 11 March 2012.
- ↑ Suid, Lawrence H. The Army's Nuclear Power Program: The Evolution of a Support Agency (Greenwood Publishing: 1990), page 32; accessed 11 March 2012.
- ↑ The Bulletin of the Atomic Scientists, February 1958 (Vol.14, issue 2: page 94); "News Roundup: Shippingport Reactor Generates Power" prepared by Helen C. Allison; accessed 11 March 2012.
- ↑ POWER, 15 June 2007, www.powermag.com, "Retrospective: June 1957"; citing a 1957 report on the SM-1 facility; accessed 10 March 2012.
- 1 2 Suid, The Army's Nuclear Power Program (1990), page 112.
- ↑ NBC Report, Spring/Summer 1998, Army Reactor Program (pp.4-6) "Army Reactor Office: The Second Year"; by US Army Major Brent B. Bredehoft, Assistant Manager, Army Reactor Program; accessed 10 March 2012.
- ↑ Federation of American Scientists, "Highly Enriched Uranium", "Appendix D: Military Reactors"; accessed 10 March 2012.
External links
- US Army's official thumbnail history of the SM-1 at Fort Belvoir, see: "Historic Fort Belvoir: Post-World War II: 1946 - Present". Archived from the original on 2012-02-12.