Lee Tunnel

Lee Tunnel
Overview
Official name Lee Tunnel
Coordinates 51°31′51″N 0°00′03″W / 51.5307°N 0.000835°W / 51.5307; -0.000835Coordinates: 51°31′51″N 0°00′03″W / 51.5307°N 0.000835°W / 51.5307; -0.000835
Status Open
Start Abbey Mills Pumping Station
End Beckton Sewage Treatment Works
Operation
Work begun 2010
Constructed MVB JV consortium
Opened 28 January 2016
Owner Thames Water
Operator Thames Water
Technical
Length 6.9 km (4.3 mi)
Highest elevation −75 m (−246 ft) at Abbey Mills
Lowest elevation −80 m (−260 ft) at Beckton
Width 7.2 m (24 ft)

The Lee Tunnel, also known as the East Ham to Stratford deep tunnel, is a tunnel in East London for storage and conveyance of sewage mixed with rainwater. The tunnel is part of the Thames Tideway Scheme and runs from Abbey Mills Pumping Station down to Beckton Sewage Treatment Works under the London Borough of Newham.

This 6.9 km (4.3 mi) long tunnel, of diameter 7.2 m (24 ft), running from 75 m (246 ft) deep at Abbey Mills down to 80 m (260 ft) deep at its terminus at Jenkins Lane, East Ham, will capture 16,000,000 m3 (1.6×1010 l), or 16 million tonnes, of sewage annually from the single largest polluting CSO in London. This sewage would otherwise flow straight into the River Lea, the Thames Tideway and eventually the Thames Estuary. However, the sewage will now be pumped up to the Beckton Sewage Treatment Works – the largest sewage treatment works in Europe – and the resultant clean water will be emptied into the River Thames. The reason for starting at −75 m is to be ready to collect sewage from the lowest point of the Thames Tideway Tunnel, which is under construction and intended to connect.

Thames Water awarded the construction contract to the MVB JV consortium, comprising Morgan Sindall, VINCI Construction Grands Projets and Bachy Soletanche, in January 2010. The cost was an estimated £635 million.[1]

The construction of the tunnel began with sinking of vertical shafts in 2010. In February 2012, the TBM, built by Herrenknecht and named Busy Lizzie, started work at the Beckton end. In 2013, a UK record concrete slipform pour was achieved, with 29 days of continual pouring.[2] The tunnel is the deepest tunnel ever bored in London, exceeding the Crossrail excavations.[2] The TBM reached Abbey Mills in January 2014.[3][4] The tunnel was completed, and opened by Mayor of London Boris Johnson, in January 2016.[5]

References

  1. "Lee Tunnel – London Tideway Improvements". Thames Water. 10 February 2014. Retrieved 8 May 2014.
  2. 1 2 "Engineering the Lee Tunnel and shafts through chalk at depth". Geological Society (PDF). Retrieved 13 May 2014.
  3. "Thames Water's Lee Tunnel completed on time and on budget". Water Briefing. Retrieved 13 May 2014.
  4. "Lee Tunnel project running 'on time and budget'". Utility Week. Retrieved 13 May 2014.
  5. "Tunnel Opened by Boris Johnson". Huffington Post. Retrieved 28 January 2016.