Lake Shannon

Lake Shannon

Lake Shannon looking downstream during the floods of 2003, with the Lower Baker Dam in the distance
Location North of Concrete, Skagit County, Washington, US
Coordinates 48°32′51″N 121°44′28″W / 48.54750°N 121.74111°W / 48.54750; -121.74111Coordinates: 48°32′51″N 121°44′28″W / 48.54750°N 121.74111°W / 48.54750; -121.74111
Type Reservoir
Primary inflows Baker River, Thunder Creek, Sulphur Creek, other small tributaries
Primary outflows Baker River
Catchment area 270 square miles (700 km2)
Basin countries United States
Built April 1, 1924 (1924-04-01)
First flooded September 1, 1925 (1925-09-01)
Max. length 7.5 miles (12.1 km)
Max. width 1 mile (1.6 km)
Surface area 2,190 acres (8.9 km2)
Average depth 70 feet (21 m)
Max. depth 280 feet (85 m)
Water volume 161,470 acre feet (199,170,000 m3)[1]
Surface elevation 436 feet (133 m) at full pool
Frozen In winter
Islands 1, unnamed, near north end
Settlements Concrete

Lake Shannon is a long, narrow reservoir on the Baker River in Skagit County in the U.S. state of Washington.[2] Formed in the 1920s by the construction of an arch dam just above the river's mouth, the lake is approximately 7.5 miles (12 km) long and averages 0.6 miles (1 km) wide at full extent. Lake Shannon is part of a cascade of two reservoirs, the Baker River Hydroelectric Project, built on the lower half of the Baker River by Puget Sound Energy for generating hydroelectricity. The reservoir is located just outside the western boundary of North Cascades National Park and just north of Concrete.

Historically Lake Shannon did not exist and Baker Lake was smaller, and the Baker River area was used primarily for fur trapping, logging, and concrete making. The formation of the lake led to problems with migrating salmon in the Baker River, which would often exceed 20,000 annually. A fish passage system was begun in the 1950s and completed in 1959 after the construction of Upper Baker Dam, the uppermost Baker River reservoir. The lake has an abundant population of kokanee salmon, the by-product of salmon spawning in lake tributaries. Fishing, boating and water skiing are popular activities on the lake, which partially lies in the Mount Baker National Forest.

Description

The Baker River flows southeast and south for about 30 miles (50 km) to meet the Skagit River at Concrete. Less than 1 mile (1.6 km) above its mouth, a 285-foot-high (87 m) arch dam, the Lower Baker Dam, straddles an extremely tight and narrow gorge to form Lake Shannon, a 2,190-acre (8.9 km2)[3] lake.

The lake occupies a cleft in the Baker River Valley between a prominent river terrace to the west and a less obvious one on the east. While the west slope directly above the lake is dissected with many canyons, the east slope is smaller and smoother. The lake is surrounded by prominent forested mountains, but the surrounding terrain is not as steep and rugged as the upper watershed.[4]

The reservoir is widest in the lower half and especially in a stretch about 3 miles (5 km) upstream of the dam. Near the middle, the lake narrows dramatically as it squeezes between the west shore and a narrow promontory that juts out into the valley. The upper half of the lake is very narrow, and the far upper end protrudes into the Mount Baker National Forest. Just above the north end of the lake, the Upper Baker Dam blocks the Baker River once again to form an expanded Baker Lake.[5]

The dominant geographical feature in the area is Mount Baker, which rises 10,781 feet (3,286 m) a few miles to the northwest of Lake Shannon. Mount Shuksan, a slightly smaller peak, rises 9,127 feet (2,782 m) further to the north-northeast. Aside from the Baker River, some major streams that feed the lake are Thunder Creek (which meets the lake near the promontory that nearly severs it in half) and Sulphur Creek, which flows directly into the lake during high water.[5]

The Baker River Road runs in a northerly direction along the east side of Lake Shannon into North Cascades National Park, while the North Cascades Highway crosses the Baker River just below Lake Shannon. Although most of the inflow to Lake Shannon is from releases from Upper Baker Dam, it also receives inflow from 82 square miles (210 km2) of adjacent watershed.[3]

Dams and facilities

An arch dam straddles a narrow, forested canyon above a tumbling river
Lower Baker Dam from the river below

The Lower Baker Dam (48°32′51″N 121°44′28″W / 48.54750°N 121.74111°W / 48.54750; -121.74111 (Lower Baker Dam)) was constructed in 1925 as the first of two dams that generate power for the Baker River Hydroelectric Project, owned by Puget Sound Energy. It is a thick-arch dam 285 feet (87 m) high and 550 feet (170 m) in length. The spillways are over the crest, consisting of about twenty-four openings. A penstock diverts water from the lake to a powerhouse on the left bank of the river, which generates 79 MW of power, and returns the water to the river just downstream of the dam. This results in a stretch of river that is nearly dry most of the time.[6] The full pool elevation of the lake is 438 feet (134 m), while the minimum lake level for power generation is 370 feet (110 m) and dead pool elevation is 355 feet (108 m).[3] The lake holds 161,470 acre feet (199,170,000 m3)[1] of water at full pool.[7]

Below the Lower Baker Dam, another structure — the "fish passage structure" — exists as the river flows through the town of Concrete. This concrete weir is the first stage in a fish elevator and flume that carries anadromous fish upstream to Baker Lake, where they are released into the water and allowed to swim upstream to the Baker River's remaining spawning grounds.[8]

History

Further information: Skagit River

Prior to the construction of the Baker River project, Lake Shannon did not exist and Baker Lake was a smaller lake formed by a glacial moraine. Anadromous fish would migrate up the Baker in numbers of up to 20,000 each spring. In the 19th century, the Baker River area was primarily used for the timber industry. Large deposits of lime around the mouth of the Baker River were taken advantage of by a cement plant built in present-day Concrete.[9]

Map of the Skagit River drainage basin showing Lake Shannon on the Baker River (near center)

On April 1, 1924,[10] the Lower Baker Dam was official begun by the Stone & Webster Company, in a site known as Eden Canyon. At first, 150 men worked on the project, which grew to a workforce of 900 by the next year.[11] In early 1925, the Lower Baker Dam was completed to a height of 230 feet (70 m) by a construction crew of 1,300, and in November of that year, the reservoir first filled to capacity.[3] (The dam was later raised 55 feet (17 m) to its present height.) The filling of the reservoir inundated the first railroad bridge across the river, the Baker River Bridge, a 190-foot (58 m)-high wooden trestle.[12] The first power generated at the dam was on November 19, 1925.[13]

The construction of the dam and the forming of the reservoir had serious impacts on the salmon of the Baker River — the dam left only 1 mile (1.6 km) of river accessible to returning salmon. Before the dam was built, in many years, over twenty thousand salmon would return to the river to spawn. Afterwards, the returning population rarely would top 3,000 fish, and decreased even more in the 1980s, culminating in a record low of 99 fish in 1985.[14] A structure was constructed across the lower Baker River below Lake Shannon, and this was originally used to capture returning anadromous fish and in conjunction with a few other facilities, carried fish up into Lake Shannon until 1959, when the system was extended to place the fish in Baker Lake instead.[15]

On July 9, 1959, Upper Baker Dam was completed and the inflow to Lake Shannon became regulated for the first time. A major landslide in 1965 crushed the Lower Baker powerhouse and its two turbines, Units 1 and 2. Units 3 and 4 were constructed near the same spot, and the original, 990-foot (300 m)-long penstock was lengthened by 420 feet (130 m), to 1,410 feet (430 m), to reach the new powerhouse.[16] This new structure was built with a sloped roof to minimize potential damage. In 1991, a water diversion project, the Koma Kulshan Project, diverted about 120 cubic feet per second (3.4 m3/s) from two west-bank Lake Shannon tributaries to Baker Lake.[3]

Natural history

One of the most abundant fishes in Lake Shannon is kokanee salmon, but this population is said to differ from true kokanee. True kokanees are established in freshwater, but the kokanees of Lake Shannon may be the by-product of sockeye salmon and coho salmon that spawned in tributaries of the lake — including Sulphur Creek and Thunder Creek — either via natural spawining gravels or artificially constructed ones. Some of the fry escaped the conduits that carry outmigrating young salmon into the lower Baker and the Skagit, establishing a population of kokanee.[17] There is also a population of bull trout present in the lake.[18]

The Lake Shannon area is dominated by Douglas fir and other coniferous and deciduous woodlands.[4]

Recreation

Lake Shannon is about 1 mile (1.6 km) north of Concrete and 35 miles (56 km) east of Mount Vernon. The lake itself is mostly accessed by following the Baker River Road, which actually leads upstream along the valley to the boundary of North Cascades National Park. Parts of Lake Shannon are within the Mount Baker National Forest, which also contains all of Baker Lake. Swimming, boating and water-skiing are available on the lake, and kokanee salmon is abundant. However, the only access to the Lake Shannon boat launch area involves passing through privately owned land.[19] The lake is open for fishing from the last Saturday of April until the 31st of October in most years.[18] There are plans to extend the current hiking trail system surrounding the two reservoirs by 8 miles (13 km)[20][21] and other general improvements within the hydroelectric project area.[22]

See also

References

  1. 1 2 http://wa.water.usgs.gov/realtime/adr/2000/data/12193000.2000.sw.pdf
  2. "Lake Shannon". Geographic Names Information System. United States Geological Survey. 10 September 1979. Retrieved 2009-09-01.
  3. 1 2 3 4 5 "Baker River Project — Initial Consultation Document, Existing Conditions, Chapter 3-3" (PDF). Puget Sound Energy. March 2002. Retrieved 2009-09-01.
  4. 1 2 "Baker River Project — Initial Consultation Document, Existing Conditions, Chapter 3-11 (Aesthetic Conditions)" (PDF). Puget Sound Energy. March 2002. Retrieved 2009-09-01.
  5. 1 2 USGS Topo Maps for United States (Map). Cartography by United States Geological Survey. ACME Mapper. Retrieved 2009-10-29.
  6. "Baker River Hydroelectric Project" (PDF). Puget Sound Energy. Retrieved 2009-08-31.
  7. "Lower Baker Dam/Lake Shannon" (PDF). Skagit River History Website. 14 June 2006. Retrieved 2009-09-01.
  8. "PSE's New Baker River $50 Million Fish Passage System Generating Success in First Few Weeks of Operation". redOrbit. 19 May 2008. Retrieved 2009-09-01.
  9. "Baker River Project — Initial Consultation Document, Existing Conditions, Chapter 3-1" (PDF). Puget Sound Energy. March 2002. Retrieved 2009-09-01.
  10. "Great New Baker Plant Completed in Record Time" (PDF). The Concrete Herald. November 26, 1925. Retrieved 2009-09-02.
  11. Kunzler, Larry (22 May 2005). "Historical Record of Dam Building and their Impacts on Floods of the Skagit River - 1924 through 1968". Skagit River History Website. Archived from the original on July 16, 2011. Retrieved 2009-09-01.
  12. "Photos of logging and cement trains and trestles in old Concrete, Washington". Skagit River Journal. The Stump Ranch. Retrieved 2009-09-01.
  13. "First Power from Baker River Plant Turned Out Today" (PDF). The Concrete Herald. November 19, 1925. Retrieved 2009-09-01.
  14. Pryne, Eric (6 September 1994). "Baker River Salmon Pass While Other Fish Runs Fail — Imperiled Sockeye Return to Spawn in Record Numbers". The Seattle Times. Retrieved 2009-09-01.
  15. "Puget Sound Energy's Fish-Enhancement Efforts Contribute to Record Half-Million Baker River Juvenile Salmon Heading to Sea". EarthTimes. 16 June 2009. Retrieved 2009-09-04.
  16. Fisk, Paul S.; Guardia, Roberto; Porter, Wayne. "Lower Baker Tunnel Investigation and Repairs" (PDF). NDT Corporation. Retrieved 2009-09-01.
  17. "Baker River Sockeye". Washington Department of Fish and Wildlife. Archived from the original on August 5, 2008. Retrieved 2009-09-01.
  18. 1 2 "Washington Fishing Prospects". Washington Department of Fish and Wildlife. Archived from the original on September 9, 2007. Retrieved 2009-09-01.
  19. Koenings, Jeffrey (March 4, 2005). "Director's report to the Fish and Wildlife Commission". Washington Department of Fish and Wildlife. wdfw.wa.gov. Archived from the original on January 13, 2010. Retrieved 2009-09-04.
  20. "Baker River, Washington: 2004 Settlement Agreement Signed for 2 Dams" (pdf). U.S. National Park Service. Retrieved 2009-09-02.
  21. "Puget Sound Energy says the new license would require spending $360 million over 30 years". Foundation for Water and Energy Education. Retrieved 2009-09-04.
  22. "PSE Awarded New 50-Year License for Baker Hydropower Facility: Years of Collaborative Negotiation Led to Comprehensive Relicensing Agreement for Low-Cost Power, Improved Flood Control, Fish Protection and Public Recreation". BusinessWire. October 20, 2008. Retrieved 2009-09-01.

External links

This article is issued from Wikipedia - version of the 10/11/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.